Pilasters

(1)  Pilasters shall be provided under beams that frame into unit masonry foundation walls 140 mm or less in thickness.     (2)  Pilasters required in Sentence (1) shall be not less than 90 mm by 290 mm and shall be bonded or tied into the wall.     (3)  The top 200 mm of pilasters required in Sentence (1) […]
Read more

Placement of Backfill

Placement of Backfill (1)  Backfill shall be placed to avoid damaging the foundation wall, the drainage tile, drainage layer, externally applied thermal insulation, waterproofing and dampproofing of the wall. Article 9.12.3.1 Ontario Regulation 332/12 Building Code,   Information published by oncodes.ca for educational purposes only.
Read more

Placing Concrete

Placing Concrete Place concrete into forms continuously in horizontal lifts not exceeding 1.2 m (4 ft.) in depth. Do not allow concrete to fall into the forms from a height of more than 2.4 m (8 ft.) as this causes the concrete to segregate. For higher drops, use a pipe to deposit the concrete. Buggies, […]
Read more

Precautions During Excavation

Precautions During Excavation (1)  Every excavation shall be undertaken in such a manner to prevent damage to adjacent property, existing structures, utilities, roads and sidewalks at all stages of construction. (2)  Material shall not be placed nor shall equipment be operated or placed in or adjacent to an excavation in a manner that may endanger the integrity […]
Read more

Preparation of Surface dampproofing

Preparation of Surface dampproofing (1)  The area in which dampproofing is to be carried out shall be kept free of water during the application and curing of the dampproofing system.     (2)  The surface to be dampproofed shall be prepared in accordance with the instructions of the dampproofing material manufacturer.     (3)  Where the dampproofing material is to […]
Read more

Preparation of Surface waterproofing

Preparation of Surface waterproofing (1)  Surfaces to be waterproofed shall be prepared in accordance with the instructions of the waterproofing material manufacturer.     (2)  Where the waterproofing material is to be applied on insulating concrete form (ICF) walls, the instructions of the ICF wall manufacturer shall be followed.     (3)  Unit masonry walls that are to be waterproofed […]
Read more

Prevention of Damage Due to Frost (steps)

Prevention of Damage Due to Frost for Cantilevered Precast Concrete Steps (1)  Suitable precautions shall be taken during backfilling and grading operations to ensure that subsequent freezing of the soil will not cause uplift forces on the underside of cantilevered concrete steps to the extent that the steps or the walls to which they are attached […]
Read more